5-2 Construction Progress

Building 1 (2349-51)- HVAC materials are currently being stocked   Building 2 (2317-19)- The plumber has begun work in the units   Building 3 (2341-47)- Plumbing is complete in all units. Siding has started on the garage side of the units and the electrician has begun rough work.   Building 4 (2321-27)- The last [...]

2017-05-02T21:02:38+00:00

4-25 Update

Building 1 (2349-2351) – Exterior sheer inspection will be happening today. Building 2 (2319-2317) – HVAC is complete, siding will start soon, they are also starting to stock insulation. Building 3 (2341-2347) – The South and East sides have received siding and they are now working on the West Side. HVAC is complete through [...]

2017-04-25T16:56:16+00:00

4-18 Construction Progress

Building 6 (2329-2333) – Units are waiting on electricians and then will go through punch walksBuilding 5 (2335-2339) – Tile is going in throughout units. Hardwood will be complete on Thursday and cabinets will be set next weekBuilding 4 (2321-2327) – Drywall is complete through two units and is progressing in the 3rd. The exterior [...]

2017-04-18T19:58:39+00:00

3-28 Construction Progress

Units in Building 6 have been painted Units in Building 5 have drywall/ mud and tape installed Units in Building 4 continue with Electrical work and some are stocking drywall Units in Building 3 continue with HVAC and Plumbing work Framing continues in Building 2 including stairs to the [...]

2017-03-29T19:43:44+00:00

3/22 Progress

Rough mechanical and electrical work in Building 4 Backsplashes and interior paint in Building 6 Drywall being hung in Building 5 Windows preparing to be hung in Building 3 First floor framed in Building 1 Framing to rooftop deck in Building 2 [...]

2017-03-22T22:08:02+00:00

1/23 Construction Progress

West Buildings: Drywall crews are 95% complete in the last of the three units in the South West building and will immediately be moving into the Northwest building following completion.Middle Buildings: Framing on the first floor of the north middle building is complete and framers have moved on to the two street facing buildings as [...]

2017-01-23T17:20:27+00:00

12/23 Progress

Across the entire project, significant underground utilities and grading continues. This is a fairly complex site, and the GC has done an exceptional planning job with the hopes that overall site concrete and flatwork will be complete prior to the completion of the first building so closings can happen as quickly as possible. West [...]

2016-12-23T21:24:33+00:00

12/9 Construction Progress

In the western buildings, the installation of rough mechanical, electrical, and plumbing work continues. We will be calling for inspections and moving into insulation and drywall shortly. Framers continue to advance the middle buildings and are nearing completion on the South middle building.

2016-12-14T17:04:58+00:00