12/23 Progress

Across the entire project, significant underground utilities and grading continues. This is a fairly complex site, and the GC has done an exceptional planning job with the hopes that overall site concrete and flatwork will be complete prior to the completion of the first building so closings can happen as quickly as possible.

West Buildings:
Draft Stop and Insulation is currently being installed in these buildings and Rough MEP should be complete by the end of this week. The next big milestones will be installation of insulation (batt and spray foam) and should be quickly followed by drywall going in.

Middle Buildings:
Framing continues and is nearing completion on the South middle building of this project. We should be starting in on installation of rough Mechanical and Plumbing in the upcoming weeks.