1/23 Construction Progress

West Buildings:
Drywall crews are 95% complete in the last of the three units in the South West building and will immediately be moving into the Northwest building following completion.

Middle Buildings:
Framing on the first floor of the north middle building is complete and framers have moved on to the two street facing buildings as planned. They will be returning to the north middle building after finishing the first floors of the two front buildings.

East Buildings:
Framing has begun on the two East (street facing) buildings. The General Contractor has scheduled the first floor of framing to be completed on the three remaining buildings simultaneously, so that structural steel can be installed at the same time. Following completion of the first floor of framing, framers will then return to completing each building one by one, with the north middle building ahead of the two street facing duplexes.