3-28 Construction Progress

Units in Building 6 have been painted

Units in Building 5 have drywall/ mud and tape installed

Units in Building 4 continue with Electrical work and some are stocking drywall

Units in Building 3 continue with HVAC and Plumbing work

Framing continues in Building 2 including stairs to the roof.

Framing is up to the third floor in Building 1