4-18 Construction Progress

Building 6 (2329-2333) – Units are waiting on electricians and then will go through punch walks

Building 5 (2335-2339) – Tile is going in throughout units. Hardwood will be complete on Thursday and cabinets will be set next week

Building 4 (2321-2327) – Drywall is complete through two units and is progressing in the 3rd. The exterior gas ditch is being dug as well

Building 3 (2341-2347)– Siding is being hung on the south side of the units

Building 2 (2317-2319) – Exterior sheathing is being installed and windows and doors are being hung

Building 1 (2349-2351) – Workers are beginning the backout for framing