5-31 Progress Update

6- Building six has seen no change from last week.

5- The plumber is beginning trim work. All backsplashes have been installed and crews are prepping the last unit in this building for paint.

4- All cabinets are set in this building. The door and trim work are complete throughout all units and paint will begin soon.

3-The Electrician has finished in this building. Foam and graph are stocked and insulation will also begin this week.

2-The electrician has begun work in this building and backout work for framing has also occurred

1- HVAC work has started in this building

Concrete framing has begun between buildings, and garage aprons for building 5 are being prepared and poured this week.