7-6-17

6 – This building has been closed out and will no longer be reported in weekly updates.

5- Crews are working on punch items and shower doors have been installed.

4- All units have been painted except for the last unit which is receiving texture.

3- All units have been dry-walled to screws.

2-Exterior work has been completed on this building.

1 – Concrete has been poured for the patios and frames are set for the exterior stairs.

Sitework continues throughout the project. Front retaining walls, pathways, and stairs are being prepared or poured. The South alley is being torn up to be replaced as well.