Construction Progress 2016-12-20T18:44:06+00:00

4-18 Construction Progress

Building 6 (2329-2333) – Units are waiting on electricians and then will go through punch walksBuilding 5 (2335-2339) – Tile is going in throughout units. Hardwood will be complete on Thursday and cabinets will be [...]

3-28 Construction Progress

Units in Building 6 have been painted Units in Building 5 have drywall/ mud and tape installed Units in Building 4 continue with Electrical work and some are stocking drywall [...]

3/22 Progress

Rough mechanical and electrical work in Building 4 Backsplashes and interior paint in Building 6 Drywall being hung in Building 5 Windows preparing to be hung [...]

1/23 Construction Progress

West Buildings: Drywall crews are 95% complete in the last of the three units in the South West building and will immediately be moving into the Northwest building following completion.Middle Buildings: Framing on the first [...]

12/23 Progress

Across the entire project, significant underground utilities and grading continues. This is a fairly complex site, and the GC has done an exceptional planning job with the hopes that overall site concrete and flatwork [...]

12/9 Construction Progress

In the western buildings, the installation of rough mechanical, electrical, and plumbing work continues. We will be calling for inspections and moving into insulation and drywall shortly. Framers continue to advance the middle buildings and [...]